Part 3: Materials and Construction Practices for
Commercial Pavements and Driveways
This is the third article in a series that provides
information on long lasting asphalt pavements for commercial parking
lots and driveways. The
first article provided an overview of the basics associated with
these pavements. The
second article covered foundation and structural design practices(subgrade
preparation, drainage and thickness design). This article covers
materials selection and construction practices.
Selecting the appropriate mixes and following good construction
practices is critical to achieving long-term performance of commercial
pavements and driveways. The appropriate asphalt mixtures for these
applications are not the same as those used for high traffic
installations.
The construction details for commercial pavements and driveways are
similar to those used for highways. Careful workmanship, attention to
detail, good compaction procedures, etc., all influence pavement
performance, regardless of traffic level.
Definition of Terms
It is important that all parties understand what is expected of the
paving job. Some of the commonly used terms are defined as follows:
- Base Course. The base course is the lower
asphalt course (or courses), below the surface and any leveling
course. The base course provides the strength of the pavement and
typically has an aggregate top size of 3/4 to 1 inch.
- Tack / Prime Coat. The tack or prime coat is a
spray applied application of emulsified asphalt. A prime coat is
applied to an aggregate base to coat and bind particles on the
surface of the aggregate layer and to promote bonding between the
aggregate and asphalt base layers. A tack coat is used to create a
bond between asphalt layers.
- Leveling Course. A leveling course is a thin
layer of an asphalt mixture that is applied over an existing
pavement to correct surface irregularities. The gradation of this
mix varies depending on the thickness needed. The aggregate top size
should not exceed the largest particles of the surface mix.
- Surface Course. The surface or wearing course
is the top course of the pavement that acts as the riding surface
and protects the underlying pavement structure.
- Pavement Thickness. The pavement thickness is
the final, compacted thickness of the particular course, rather than
the loose thickness of the mat prior to compaction.
Materials for Driveways
The asphalt mixtures used for paving driveways do not typically have
to carry the loads associated with more heavily traveled pavements. For
driveways, the base mix provides the support, and the surface mix should
be sufficiently workable to provide a finished surface that is smooth
and uniform.
The asphalt mixes typically consist of a blend of uniformly graded
aggregate and an asphalt binder suited for local weather conditions. For
driveways, mixes containing modified binders are not needed and should
generally be avoided because these mixes may be difficult to hand-work
and may result in open textured pavement surfaces. The coarse aggregate
should be sound, angular crushed gravel, stone, or slag and the fine
aggregate should be a well graded, moderately sharp to sharp sand.
Driveway mixes should be based on a mix design having about 3.5
percent air voids using a laboratory compactive effort suited for low
traffic pavements. The base mix should be a well graded blend of
aggregates that has a proven performance history. The selected surface
mix should result in a pavement with a fine graded appearance and thus
have reduced potential for segregation and water penetration from low
in-place densities. The surface mix should contain some stone (rather
than being an all sand mix) to minimize scuffing and punching
depressions.
The base for driveways should use a 3/4- to 1-inch top size
aggregate, and the surface mix should have a top size of 3/8 inch.
Typical thicknesses for base courses are 3 to 4 inches; the surface
course should be 1 to 1.5 inches. It is critical to recognize that all
pavement thicknesses are in terms of the final, compacted thicknesses,
rather than the loose thickness behind the paver.
Materials for Parking Lots
The materials for commercial parking lots are generally similar to
those for driveways. There may be thicker, or more, base courses for
selected areas of the commercial development that experience
concentrated traffic. Examples of these locations include
loading/delivery areas, dumpster pads, etc. For worst-case loading
applications, such as dumpster pads, it is advisable to consult an
engineer for advice concerning materials containing mixes with a high
degree of stone-to-stone contact and/or modified binders.
Where thicker courses are used, an aggregate with a top size of 1
inch can be used. (For guidance on thickness/structural design, see
Part 2 of this series, published in Spring 2008.) Surface mixes for
commercial pavements should be placed at 1.5 inches and contain up to
1/2-inch top size stone.
Construction of Driveways
It is important that the subgrade is stable before beginning paving
operations. For any backfilled areas, make sure that the soil is well
compacted and that any settlement has ended. A loaded dump truck or
similar vehicle can be driven over the subgrade as a proof roller to
ensure that the foundation is stable. After finishing the subgrade, the
aggregate base is placed, shaped and compacted.
Paving should be done only when weather conditions are good—not in
cold or rainy weather. Compaction is critical to pavement performance,
and the time to compact the mix is greatly reduced during cool or wet
conditions. The compaction equipment should be sized to the job.
Driveway jobs can be compacted with relatively small rollers (3 to 5
tons).
The contractor needs to work closely with the HMA producer to manage
the temperature of the HMA. To avoid damaging the mix, it should not be
overheated. But the mix temperature should be maintained at a level that
allows thorough compaction. Similarly, during the entire operation, the
contractor must manage the material handling and placement to avoid
segregation. Hand-work should be minimized. As much as possible, let the
paving machine do the work. Use extra care with construction of all
joints.
Construction Practices for Commercial Pavements
For large commercial jobs, it may be worthwhile to name a
“Person-in-Charge” who will oversee the project. This individual should
know asphalt design, production, and installation.
All of the construction details described for driveways applies for
commercial applications. Additionally, it is recommended that the
surface course be placed all in one day, wherever possible. If it is not
possible to complete the surface paving, it will be necessary to make a
construction joint. Other important points include good handling
practices such as managing segregation, minimizing raking and avoiding
back-scattering of collected coarse particles.
For sizable commercial pavements, density testing may be appropriate.
Generally, the pavement should be compacted to 92 percent or more of
maximum density. Longitudinal joint density should exceed 90 percent.
The thicker pavements of some parking lots may need heavier (and more)
rollers.
Conclusion
Asphalt parking lots and driveways that are built with good materials
and construction practices offer good performance and value to their
owners. The process is not difficult; it just takes an understanding of
the principles and a commitment to doing things right.
Tim Murphy is the principal of
Murphy Pavement Technology.
Dwight Walker is the editor of Asphalt Magazine.